Construction Cost Per Square Foot (2025)

For quality modern construction:

  • Standard build: $250-300/sq ft

  • Mid-range build: $300-350/sq ft

  • High-end build: $350-500/sq ft

But construction is only part of the total cost.

What a 2,500 Square Foot Modern Home Actually Costs

Construction: 2,500 sq ft @ $325/sq ft = $812,500

But you also need:

Land: $350,000-1,200,000

  • Varies dramatically by location

  • Outer suburbs: $350-500K

  • Close-in suburbs: $500-750K

  • Premium locations: $700K-1.2M+

Permits & Fees: $30,000-60,000

  • Montgomery County tends higher (impact fees)

  • Northern Virginia varies by jurisdiction

  • Building permits, impact taxes, reviews

Site Preparation: $30,000-100,000

  • Flat lots: $30-50K

  • Sloped lots: $50-100K (retaining walls, grading)

  • Depends on your specific site

Architect & Engineering: $75,000-100,000

  • Typically 10-12% of construction cost

  • Includes design, permits, construction oversight

Landscaping: $40,000-90,000

Contingency (10%): $80,000

TOTAL ALL-IN: $1.4M - $2.4M

The wide range depends on:

  • Where you're building (land costs vary wildly)

  • How challenging your site is

  • What finishes you choose

Three Real Budget Scenarios

Budget Option: ~$1.2M - $1.4M

  • Size: 2,200 sq ft

  • Construction: $275-290/sq ft

  • Land: $400-500K (outer suburbs)

  • What you get: Well-designed modern home, good finishes, energy-efficient

Mid-Range: ~$1.6M - $1.9M

  • Size: 2,500 sq ft

  • Construction: $325-350/sq ft

  • Land: $550-700K (close-in suburbs)

  • What you get: Custom modern home, upgraded finishes, high-performance systems

Premium: ~$2.2M - $2.6M

  • Size: 3,000 sq ft

  • Construction: $375-425/sq ft

  • Land: $850K-1.2M (premium locations)

  • What you get: Luxury modern home, designer finishes, exceptional details

What Drives Your Cost

The Big Variable: Land

Land costs vary more than anything else:

Examples in our service area:

  • Gaithersburg/Germantown: $350-450K

  • Rockville/Reston: $500-650K

  • Bethesda/Falls Church: $650-900K

  • Chevy Chase/Arlington: $700K-1.2M+

Your commute requirements largely determine this cost.

Site Conditions

Flat lot with easy access: $30-50K in site work

Sloped lot: $50-100K in site work

  • Retaining walls

  • Complex grading

  • Erosion control

Challenging site: $100K+ in site work

  • Significant slopes

  • Rock excavation

  • Poor soil conditions

  • Difficult access

Design Complexity

Simple modern design: Base construction cost

Complex design: +$50-100/sq ft

  • Multiple roof planes

  • Extensive built-ins

  • Complex geometry

  • Heavy use of glass

Finish Level

Standard finishes: Base construction cost

Premium finishes: +$30-75/sq ft

  • Custom millwork

  • High-end appliances

  • Imported tile

  • Designer fixtures

Permit Costs Vary by Location

Montgomery County: $40,000-60,000

  • Higher impact fees

  • School facilities surcharge

  • More expensive than most areas

Northern Virginia: $30,000-50,000

  • Varies by county (Arlington vs. Fairfax vs. Loudoun)

  • Some neighborhoods have ARB fees

  • Generally lower than Montgomery County

Project Timeline

Total: 18-24 months

  • Design: 3-4 months

  • Permitting: 3-5 months

  • Construction: 10-14 months

Historic districts add 2-4 months to permitting.

Architectural Fees

10-12% of construction cost

For an $800K construction budget: $80,000-96,000

What this includes:

  • Complete design

  • Permit drawings

  • Construction oversight

  • Problem-solving during build

Good design saves money by solving problems on paper instead of during construction.

What's NOT Included in These Numbers

Don't forget to budget for:

  • Furniture: $50-100K

  • Window treatments: $10-20K

  • Moving costs: $5-10K

  • Temporary housing during construction: Varies

  • Construction loan interest: ~$25-40K for a $800K loan

How to Get Accurate Numbers for YOUR Project

Every site is different. Your actual costs depend on:

  • Your specific lot and its challenges

  • Local jurisdiction requirements

  • Your finish preferences

  • Current market conditions

Generic estimates only get you so far.

Our Modern Vision Assessment: $2,500

(Fully credited toward design fees if you proceed)

What you get:

  • Real cost estimate for YOUR specific site

  • Zoning verification

  • Site assessment

  • Budget breakdown

  • Alternatives if budget is tight

Why this matters: One consultation typically saves $50-100K by catching budget issues before you invest in full plans.

Real example: Client budgeted $1.5M for a 3,000 sq ft home. Their lot had significant slopes requiring $80K in site work. We redesigned to 2,400 sq ft, adjusted the footprint to minimize grading, and hit their budget. Without the MVA, they would have spent $75K on full plans before discovering the problem.

Common Questions

Q: What's included in the construction cost per square foot?

A: Everything to make the house habitable: foundation, framing, roofing, exterior, windows, doors, HVAC, plumbing, electrical, insulation, drywall, finishes, flooring, kitchen, bathrooms. Does NOT include: land, permits, architecture, landscaping, furniture.

Q: Why such a wide range in total cost?

A: Mostly land. A $400K lot vs. a $1M lot is $600K difference right there. Site conditions and finishes create the rest of the range.

Q: Can I save money by being my own general contractor?

A: Not recommended unless you have construction experience. Most owner-builders spend more due to mistakes, lack of trade pricing, and coordination issues. Professional GCs charge 15-20% but typically save you that much.

Q: Is it cheaper to build now or wait?

A: Construction costs increase 3-5% annually. Waiting a year typically means paying $40-80K more on an $800K build. If you're ready, building now usually makes sense.

Q: How much do I need for a down payment?

A: Construction loans typically require 20% down of total project cost. For a $1.5M project, that's $300K.

Q: Do modern homes cost more than traditional?

A: Construction costs are similar at the same quality level. Modern homes may cost 5-10% more upfront for better insulation and windows, but save 30-40% on energy bills.

Q: What about unexpected costs?

A: This is why we recommend a 10% contingency. Common surprises: rock excavation, hidden site issues, or scope changes during construction.

Q: Where should I build?

A: Wherever is closest to your work and meets your lifestyle needs. Land costs vary, but quality of life matters more than saving $100K on a lot if it adds an hour to your daily commute.

Ready to Get Real Numbers?

These are realistic ranges, but your project is unique.

Book a Modern Vision Assessment to get actual costs for your specific situation.

$2,500 - Fully credited toward design fees

Call: 301.922.4152
Email: info@rtarchstudio.com
Website: rtarchstudio.com

We only take 5 new clients per quarter.

Serving Montgomery County, Maryland and Northern Virginia since 2013.

Next
Next

Why Modern Residential Architecture? Transform Your Living Experience